Land & Watersheds
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Land & Watersheds · [Project No.]
[Project Name]
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
·Contents
Table of contents.1 · Introduction[p]
1.1 Project description & location[p]
1.2 Scope & purpose[p]
1.3 Methodology & data sources[p]
1.4 Authorization & study area[p]
2 · Catchment characterization (GIS)[p]
3 · Hydrology[p]
3.1 Rainfall, NOAA Atlas 14[p]
3.2 Runoff modeling, GeoStorm (SWMM)[p]
4 · Hydraulics[p]
4.1 Storm-sewer conveyance[p]
4.2 Detention / retention & LID routing[p]
5 · Results & flood mapping[p]
6 · Observations & conclusions[p]
Certification[p]
List of Tables
Table 2-1 Catchment parameters
Table 3-1 NOAA Atlas 14 rainfall depths Table 3-2 Pre/post peak discharges Table 4-1 Stage-storage-discharge List of Figures
Fig 1 Effective FIRM
Fig 2 NOAA Atlas 14 PF estimates Fig 3 GIS catchment delineation Fig 4 Detention & outlet schematic Fig 5 Flood-depth map Appendices
A, NOAA Atlas 14 data D, Hydraulic / routing report
B, GIS basin parameters E, Detention & outlet calculations
C, GeoStorm hydrology report F, Figures & model results
01Introduction
Introduction.1.1 · Project description & location[Client / Owner] has requested Land & Watersheds to perform a Hydrologic & Hydraulic (H&H) study for the proposed [Project Name] development at [PR-000, Km 0.0, Barrio, Municipality], Puerto Rico. The site occupies approximately [00.0] acres and drains toward [receiving system / quebrada]. The purpose of this study is to quantify pre- and post-development stormwater runoff, size the proposed detention and Low-Impact Development (LID) mitigation, and demonstrate that the development does not adversely affect downstream conveyance. 1.2 · Scope & purpose
1.3 · Methodology & data sources
1.4 · Authorization & study areaThis study was authorized by [Client / Owner] on [date]. The study area comprises the project parcel and the immediately contributing and receiving drainage, as shown on the effective Flood Insurance Rate Map (FIRM). Figure 1 · Effective FIRMDrop FEMA FIRMette / firm panel for the site Figure 2 · NOAA Atlas 14Drop PF-estimate table / PFDS screenshot 02Catchment Characterization
Catchment characterization (GIS).The contributing catchment was delineated from best-available LiDAR topography and subdivided into [00] sub-catchments consistent with the proposed storm-sewer layout. Curve numbers were assigned from SSURGO hydrologic soil groups and NLCD/proposed land cover; times of concentration were computed by the [TR-55 / velocity] method.
Figure 3 · GIS catchment delineationDrop GeoStorm / GIS sub-catchment & parameter map 03Hydrology
Hydrology.3.1 · Rainfall, NOAA Atlas 14Design rainfall depths were obtained from NOAA Atlas 14, Volume III, for the site coordinates [lat, long], partial-duration series, for the 24-hour duration.
3.2 · Runoff modeling, GeoStorm (SWMM)Pre- and post-development runoff was modeled in GeoStorm (EPA-SWMM engine) using the NRCS dimensionless unit hydrograph. Peak discharges at the point of compliance are summarized below.
04Hydraulics
Hydraulics.4.1 · Storm-sewer conveyanceThe proposed storm-sewer network (inlets, RCP mains, manholes) was analyzed for capacity under the [10-yr] design storm. All runs convey the design flow with the hydraulic grade line below rim elevations, except as noted. 4.2 · Detention / retention & LID routingThe detention pond (bottom el. [00.00 ft], [2H:1V] slopes) was routed by the Storage-Indication method. The outlet structure combines a [orifice] and [weir] sized so post-development peaks do not exceed pre-development peaks.
Figure 4 · Detention & outlet schematicDrop pond grading / outlet-structure detail or stage-storage curve 05Results & Flood Mapping
Results & flood mapping.Where surface ponding or 2D behavior governs, a GeoStorm 2D surface model was developed over the project terrain. Maximum flow depths and velocities for the [100-yr] event are mapped below; the mitigated condition keeps water surfaces below [finished-floor / freeboard target]. Figure 5 · Max flow depthDrop 2D depth raster Figure 6 · Max velocityDrop 2D velocity raster 06Observations & Conclusions
Observations & conclusions.
Note: all designs presented herein are schematic and not for construction. Final design is subject to survey verification and permitting.
·Certification
Engineer’s certification.I hereby certify that this Hydrologic & Hydraulic Study was prepared by me or under my direct supervision, and that I am a duly licensed Professional Engineer under the laws of the Commonwealth of Puerto Rico.
P.E. SEAL
& SIGNATURE David Vagnetti, PE
Civil Site & Water Resources Engineer · License No. [#####]
Date: [Month DD, YYYY]
Site Photographs
Photo 1
Photo 2
Photo 3
|